title: PM-KUSUM Scheme 2026: Deadlines | Arrays Ingenieria
description: PM-KUSUM in 2026: solar plants on farmland, solar pumps and feeder solarisation, the support on offer, the extended deadlines and the proposed 2.0.
url: https://arraysingenieria.com/pm-kusum-scheme/
last_updated: 2026-10-11
source: Arrays Ingenieria (Arrays Ingenieria Pvt. Ltd.)
---

Guide · Schemes

# PM-KUSUM in 2026: Components A, B and C, New Deadlines and What Comes Next

India's farm solar scheme: up to 2 MW plants on farmers' land, standalone solar pumps and solarised feeders. What each component offers, the 2026 deadline extensions, and the proposed PM-KUSUM 2.0.

On this page

- What PM-KUSUM is
- The three components
- The 2026 deadlines
- What is next: PM-KUSUM 2.0
- Building a Component A or feeder plant: what matters on site
- Frequently asked questions
- Sources

By the [Arrays Ingenieria engineering team](https://arraysingenieria.com/about/) · Updated 11 Oct 2026 · 3 min read

**Key takeaways**

- **Component A:** grid-connected solar plants of 500 kW to 2 MW on farmers' land, with the power bought by the DISCOM
- **Component B:** standalone solar pumps for farms off the grid, with central and state support
- **Component C:** solarising existing grid-connected pumps, individually or by whole agricultural feeders
- 2026: financial closure for Components A and C extended to **30 November 2026**; completion by **31 March 2027**, with no further extension
- A **PM-KUSUM 2.0** with a dedicated agri-PV component has been announced but not yet launched

## What PM-KUSUM is

**Pradhan Mantri Kisan Urja Suraksha evam Utthaan Mahabhiyan (PM-KUSUM)** was launched in March 2019 to give farmers energy security and an extra income from solar, while cutting the diesel and subsidised grid power used for irrigation. It was scaled up and extended in the years since, and in 2026 it is in its final stretch.

## The three components

PM-KUSUM at a glance

| Component | What gets built | Who benefits | Support (typical) |
| --- | --- | --- | --- |
| A | Grid-connected ground- or stilt-mounted solar plants of 500 kW to 2 MW on barren, fallow or farm land, usually within 5 km of a substation | Farmers, groups, cooperatives, panchayats, FPOs, and developers on their land | DISCOM buys the power at a pre-fixed tariff; DISCOMs receive a performance-based incentive |
| B | Standalone off-grid solar pumps | Individual farmers | Central support of 30% of benchmark cost (50% in the North-East, hill states and islands), plus state support |
| C | Solarisation of existing grid-connected pumps (individual) or of whole agricultural feeders (feeder-level solarisation) | Farmers on grid-connected pumps; DISCOMs for feeders | Central support of 30% (50% in special-category states) for individual pumps; central support for feeder-level plants |

**Why feeder-level solarisation matters**

Instead of panels on every farm, a ground-mount solar plant of a few megawatts feeds an entire agricultural feeder. Farmers get daytime power for irrigation, and the plant is an ordinary utility-style build: land, piling, structures, modules, inverters and a substation connection.

## The 2026 deadlines

PM-KUSUM timelines as revised in 2026

| Milestone | Applies to | Date |
| --- | --- | --- |
| Financial closure | Components A and C | 30 November 2026 (extended from 30 September 2026) |
| Completion (commissioning) | Projects with PPA signed or NTP issued on or before 31 December 2025 | 31 March 2027; no further extension, per MNRE |
| Commissioning, individual pumps | Component B and Component C (individual pump solarisation) | 30 September 2026 under the March 2026 revision; check for later updates |

The extension of financial closure was granted because developers had trouble getting loans appraised and sanctioned in time. MNRE has said there will be no extension of the completion deadline beyond 31 March 2027, so projects that are not under construction by early 2027 are at real risk.

## What is next: PM-KUSUM 2.0

The Union Minister for New and Renewable Energy has said a **PM-KUSUM 2.0** will follow, with a dedicated component of about **10 GW for agri-photovoltaics** (solar panels raised above crops so that farming and generation share the same land). When this guide was checked the new scheme had not been formally notified, so its support levels and eligibility are not yet known.

## Building a Component A or feeder plant: what matters on site

- **Land and soil:** a soil test decides the pile design; farmland often needs deeper piles than hard ground.
- **Evacuation:** the distance to the substation and the line route drive cost and approvals.
- **Security:** chain-link fencing and lighting protect modules on open farmland.
- **Domestic content:** scheme plants must use DCR modules (see [ALMM explained](https://arraysingenieria.com/almm-list-ii-solar-cells/)).
- **Schedule:** with the March 2027 cut-off, piling and structures must start early enough to leave time for commissioning and inspection.

Civil works and chain-link fencing for a 14.36 MW solar project in Uttar Pradesh: the same site works a Component A or feeder-level plant needs.

Developing a PM-KUSUM Component A or feeder-level plant? We do piling, fencing, civil works and installation & commissioning.

[Get a free solar quote](https://arraysingenieria.com/free-solar-quote/)

## Frequently asked questions

What is PM-KUSUM Component A?

Grid-connected solar plants of 500 kW to 2 MW on farmers' land, with the power bought by the DISCOM at a pre-fixed tariff.

What is the last date for PM-KUSUM projects?

Financial closure for Components A and C has been extended to 30 November 2026, and completion is due by 31 March 2027 for projects with PPA or NTP by 31 December 2025, with no further extension.

How much subsidy is there on a solar pump?

Central support is 30% of the benchmark cost (50% in the North-East, hill states and islands), with state support on top; the farmer's share varies by state.

Has PM-KUSUM 2.0 been launched?

It has been announced, with about 10 GW for agri-photovoltaics, but it had not been formally notified when this guide was checked.

## Sources

- [PIB, 6 Aug 2024: PM-KUSUM](https://pib.gov.in/PressReleasePage.aspx?PRID=2042069)
- [Renewable Watch, 31 Mar 2026: MNRE extends timelines for projects under PM-KUSUM](https://renewablewatch.in/2026/03/31/mnre-extends-timelines-for-projects-under-pm-kusum-scheme/)
- [Energetica India: MNRE extends PM-KUSUM financial closure deadline to 30 November](https://energetica-india.net/news/mnre-extends-pm-kusum-financial-closure-deadline-to-nov-30)

This guide explains public policy in plain language for planning purposes. Rules, rates and deadlines change: confirm the current position with the notifying authority, your DISCOM and your tax adviser before you commit. Last checked 11 Oct 2026.

**About the authors.** Arrays Ingenieria is an ex-servicemen-led solar EPC and installation & commissioning company working Pan-India, from Assam's tea estates to industrial rooftops. [Our story](https://arraysingenieria.com/ex-servicemen-led-msme/) · [Our projects](https://arraysingenieria.com/projects/)

[Ground-Mount Solar](https://arraysingenieria.com/service-ground-mount/)[Pile Foundations](https://arraysingenieria.com/service-piling/)[Civil Works & Fencing](https://arraysingenieria.com/service-civil/)

From Our Sites

## Case Studies on This Topic

Real plants our veteran-led crews have built, with the scope of work in detail.

[Industrial · Civil Works: **DCM Textile, Hisar: Civil Works, Piling and I&C for Solar**9979 kWp (10 MW) · Hisar, HaryanaRead the case study](https://arraysingenieria.com/project-dcm-hisar-10mw-solar-civil-works/)[Utility-Scale · Civil & Fencing: **Noida International Airport (YIAPL): 14.36 MW Solar, Piling & Fencing**14.36 MW · Noida International Airport, Gautam Buddh Nagar, Uttar PradeshRead the case study](https://arraysingenieria.com/project-yiapl-14-36mw-solar-civil-fencing/)[Utility-Scale · Piling: **SECI 300 MW Solar Project, Koppal: Piling and DC Installation**300 MW solar project · Koppal, KarnatakaRead the case study](https://arraysingenieria.com/project-seci-300mw-koppal-pile-foundation/)

Keep Reading

## Related Guides

[Policy: **ALMM List-I and List-II Explained: The Made-in-India Rule for Solar Modules and Cells**MNRE's Approved List of Models and Manufacturers now covers solar cells as well as modules. What List-I and List-II mean, which projects they bind, the exemptions, and how to stay compliant.3 min read · Updated 11 Oct 2026](https://arraysingenieria.com/almm-list-ii-solar-cells/)[Schemes: **PM Surya Ghar: Muft Bijli Yojana 2026: Subsidy, Eligibility and How to Apply**India's rooftop solar scheme for homes: up to Rs 78,000 central subsidy, support for housing societies, low-cost loans and the national portal. What you get, who qualifies, and the steps from application to subsidy.3 min read · Updated 11 Oct 2026](https://arraysingenieria.com/pm-surya-ghar-subsidy/)[System Design: **Rooftop vs Ground-Mount Solar: Which Is Right for Your Site?**Use the roof you already have, or build on land? A practical comparison of rooftop and ground-mount solar: cost, space, structure, safety, foundations, approvals and maintenance.3 min read · Updated 11 Oct 2026](https://arraysingenieria.com/rooftop-vs-ground-mount-solar/)

[All solar guides](https://arraysingenieria.com/insights/)[Government solar schemes](https://arraysingenieria.com/solar-schemes-india/)