# DCM Textile, Hisar: Civil Works, Piling and I&C for Solar

Civil works for a 9979 kWp (10 MW) ground-mount solar plant at DCM Textile in Hisar, Haryana.

The Project

## About the DCM Hisar, Haryana project

Tata Power issued Arrays Ingenieria the work order on 18 June 2021 for civil works at the 9979 kWp plant. Tata Power has since engaged the company for piling, civil works and installation on projects across India.

DCM has been a repeat site. In 2022 Tata Power Solar engaged Arrays Ingenieria for the installation & commissioning of the 2.1 MW rooftop plant at Hisar, with its CEIG approval, module cleaning system, canopy and conventional earthing.

In 2025-26 the company piled, installed and commissioned a further 500 kWp ground-mount plant at DCM Textile for Tata Power Renewable Energy.

### Our scope of work

- Civil works and pile foundations for the 10 MW ground-mount plant
- Installation & commissioning of the 2.1 MW rooftop plant
- Canopy erection and conventional earthing
- CEIG approval and module cleaning system
- Piling and I&C of a 500 kWp ground-mount plant (2025-26)

### Photos

## Project facts

Capacity: **9979 kWp (10 MW)**

Plant type: **Ground-mount, civil works**

Location: **Hisar, Haryana**

Client: **Tata Power**

Partner / programme: **DCM Textile (plant owner)**

Our role: **Civil works, piling, installation & commissioning**

Year: **2021-2026**

## Planning a similar project?

Talk to our veteran-led team about EPC, installation & commissioning or civil works.

[Get a Free Quote](https://arraysingenieria.com/free-solar-quote/)

Project Timeline

## How the Project Unfolded

The work, stage by stage, as it was ordered and delivered.

-

Jun-Sep 2021

### 10 MW civil works

Civil works and pile foundations with pile caps for the 9979 kWp ground-mount plant, and electrical equipment foundations.

-

Apr-Jun 2022

### 2.1 MW rooftop I&C

Installation & commissioning of the 2.1 MW rooftop plant, its module cleaning system and CEIG approval.

-

Aug-Dec 2022

### BOS, canopy and earthing

Rooftop BOS services, canopy installation and conventional earthing for the 2.1 MWp plant.

-

Sep 2023

### Close-out

Hardware, glands and lugs.

-

Aug-Dec 2025

### 500 kWp ground-mount

BOS, installation & commissioning and piling for a further 500.96 kWp ground-mount plant.

On Site

## Challenges and How We Handled Them

### A repeat site over five years

DCM Textile's Hisar mill brought us back for civil works, a rooftop plant and a ground-mount plant between 2021 and 2025.

### Haryana's hard ground

Pile foundations with pile caps were designed for the site's soil and wind loads.

### Inspection and safety

CEIG approval and conventional earthing were part of the rooftop scope, so the plant was handed over inspection-ready.

Related

## Services Used on This Project

[Civil Works & Fencing](https://arraysingenieria.com/service-civil/)[Ground-Mount Solar](https://arraysingenieria.com/service-ground-mount/)[All Projects →](https://arraysingenieria.com/projects/)

More Case Studies

## Other Projects by Arrays Ingenieria

[Industrial · Piling & Civil: **Tata Motors, Jamshedpur: Piling, Civil Works and I&C for 5.5 MW Solar**5.5 MW · Jamshedpur, JharkhandRead the case study](https://arraysingenieria.com/project-tata-motors-jamshedpur-5-5mw-solar-piling/)[Utility-Scale · Civil & Fencing: **Noida International Airport (YIAPL): 14.36 MW Solar, Piling & Fencing**14.36 MW · Noida International Airport, Gautam Buddh Nagar, Uttar PradeshRead the case study](https://arraysingenieria.com/project-yiapl-14-36mw-solar-civil-fencing/)[Utility-Scale · Piling: **SECI 300 MW Solar Project, Koppal: Piling and DC Installation**300 MW solar project · Koppal, KarnatakaRead the case study](https://arraysingenieria.com/project-seci-300mw-koppal-pile-foundation/)