Solar power plant commissioning ceremony, Arrays Ingenieria
Case Study · Tea Estates · Ground-Mount I&C

Dewan Group of Tea Estates: 1940 kWp Ground-Mount Solar

Three ground-mounted, on-grid solar plants, 1940 kWp in all, for the Dewan Group of Tea Estates of Jay Shree Tea & Industries (BK Birla Group) in Cachar, Assam: 735 kWp at Dewan, 620 kWp at Burtoll and 585 kWp at Labac.

The Project

About the Jay Shree Tea, Cachar, Assam project

Arrays Ingenieria worked as the implementing partner of Tata Power Renewable Energy Ltd. (TPREL). The work order is dated 25 June 2025; the scope covered supply of the balance of system along with installation & commissioning of the 1940 kWp grid-connected solar power generation system.

Work began on 9 October 2025 and was completed on 8 January 2026, the commissioning date. In its work completion certificate of 22 January 2026, the Dewan Group of Tea Estates confirms that the plants are fully operational, have been taken over, and that performance has been verified and found to meet the agreed standards, to the complete satisfaction of the Dewan Group and TPREL.

Jay Shree Tea also issued a certificate of appreciation for each plant, citing Arrays Ingenieria's professionalism in installation and commissioning: "Their competence is indeed praiseworthy." This was the second Jay Shree Tea solar project for Arrays Ingenieria, after the 1035 kWp at Towkok and Manjushree.

Our scope of work

  • Supply of balance of system (BOS)
  • Installation of the ground-mount plants at three estates
  • Testing and commissioning of the 1940 kWp grid-connected system
  • Handover to the Dewan Group and TPREL

In the news

Project Timeline

How the Project Unfolded

The work, stage by stage, as it was ordered and delivered.

  1. Work order

    Work order for BOS supply and installation & commissioning of 1940 kWp.

  2. Work begins

    Installation starts across Dewan, Burtoll and Labac Tea Estates.

  3. Commissioned

    All three plants completed and commissioned; performance verified.

  4. Completion certificate

    Dewan Group confirms handover to its complete satisfaction and TPREL's.

On Site

Challenges and How We Handled Them

Three estates, one schedule

Dewan (735 kWp), Burtoll (620 kWp) and Labac (585 kWp) were built and commissioned together in three months, from 9 October 2025 to 8 January 2026.

Documented completion

A work completion certificate and three certificates of appreciation from the client record the result, plant by plant.

Installation & Commissioning

What Our I&C Scope Covered

The standard ground-mount installation & commissioning scope we deliver to EPC majors' specifications, after the mandatory quality and safety training and contractor safety sign-off.

Civil works

  • Earth-pit chambers and covers (RCC/PCC)
  • Foundations for inverters, ACDB, ITB and accessories
  • Cable trenches
  • Cube tests to validate concrete strength

Mechanical

  • Module mounting structure installation
  • Module installation and interconnection
  • Canopies for wall-mounted inverters and junction boxes

DC side

  • String wiring from modules to inverters, tagged and identified
  • DC cables in conduit or tray
  • MC4 connectors crimped male and female
  • Array junction boxes

AC side and protection

  • Inverters and inverter terminal boxes
  • AC distribution board (ACDB)
  • LT AC cables in trays to the approved layout
  • Reverse power relays installed and commissioned

Earthing and lightning

  • Earth electrodes and pits
  • Earthing strips for structures, inverters and ACDB, including welding
  • Lightning arrestors

Monitoring and cleaning

  • Data monitoring system (SCADA / power manager)
  • Module cleaning system with pump and motor
  • DWC pipe for RS485 communication cable

Safety and handover

  • Safety lines and safety posters
  • Material unloading, storage under covers and care until handover
  • Third-party validation of tools where required
  • Testing, commissioning and handover
Documents

Orders, Certificates & Press

The documents behind this case study. Tap to view full size.

Jay Shree Tea certificate of appreciation: 735 kWp, Dewan Tea Estate, Arrays Ingenieria
Jay Shree Tea certificate of appreciation: 735 kWp, Dewan Tea Estate
Jay Shree Tea certificate of appreciation: 620 kWp, Burtoll Tea Estate, Arrays Ingenieria
Jay Shree Tea certificate of appreciation: 620 kWp, Burtoll Tea Estate
Jay Shree Tea certificate of appreciation: 585 kWp, Labac Tea Estate, Arrays Ingenieria
Jay Shree Tea certificate of appreciation: 585 kWp, Labac Tea Estate
Talk to an engineer

Planning a solar plant? Let's build it together.

CAPEX solar EPC, installation & commissioning and civil works, delivered by an ex-servicemen-led team across India. Tell us about your site and an engineer will get back to you.