Earthing and electrical safety works on a solar plant by Arrays Ingenieria
Guide · Standards & Safety

Solar Quality and Safety Norms in India (2026): BIS, the Quality Control Order, CEA and CEIG

What makes a solar plant compliant in 2026: the BIS Quality Control Order for modules, inverters and batteries, the standards each component should meet, the Electrical Inspector's approval, and site safety.

Key takeaways
  • The revised Solar Systems, Devices and Components Goods Order, 2025 (notified 27 January 2025) requires BIS certification for modules, solar inverters and storage batteries
  • Large inverters (above 200 kW) were given extra time to certify, reportedly to the end of 2026
  • Modules must also meet ALMM where it applies (see our ALMM guide)
  • Plants above the voltage and capacity thresholds need the Electrical Inspector's (CEIG) approval before energisation under the CEA safety regulations
  • Earthing, lightning protection, surge protection and documented commissioning tests are what keep a plant safe for 25 years

Three layers of compliance

  1. Product certification: each component meets its Indian Standard and carries the BIS mark (and, for modules, ALMM where applicable).
  2. Design and installation: the plant is designed and built to the electrical safety regulations and good practice.
  3. Inspection and approval: the DISCOM and, where required, the Electrical Inspector approve the plant before it is energised.

The BIS Quality Control Order

MNRE notified the revised Solar Systems, Devices and Components Goods (Requirement for Compulsory Registration) Order, 2025 in the Gazette on 27 January 2025, effective after a 180-day transition. It covers solar PV modules, inverters for solar PV applications and storage batteries. These must conform to the notified Indian Standards and carry the BIS Standard Mark under a BIS licence; products made only for export are exempt.

Inverters above 200 kW were allowed extra time. MNRE extended the self-certification window for them, reportedly to 31 December 2026, during which makers need valid IEC certificates matching the Indian Standards.

The standards each component should meet

Common standards for solar plant components
ComponentStandards to ask forWhat they cover
Crystalline PV modulesIS 14286 / IEC 61215; IS/IEC 61730Design qualification and type approval; safety
Grid-tied invertersIS 16221 (Parts 1 and 2) / IEC 62109; IS 16169Safety of power converters; islanding-prevention test
DC cablesIS 17293 / EN 50618 type solar cablesUV-resistant, double-insulated cables for PV
AC power cablesIS 7098 (XLPE)Armoured LT cables to the distribution board
EarthingIS 3043Code of practice for earthing
Lightning protectionIS/IEC 62305Lightning protection of structures
Commissioning and documentationIEC 62446-1System documentation, commissioning tests and inspection
Storage batteriesNotified IS for the battery typeCovered by the 2025 Quality Control Order

CEA safety regulations and CEIG approval

The Central Electricity Authority's safety and electric supply regulations set the rules for electrical installations, including clearances, earthing, protection and inspection. Installations above the specified voltage, and in many states above a set capacity, must be inspected and approved by the Electrical Inspector (the Chief Electrical Inspector to Government, CEIG, in many states) before they are energised.

  1. Drawing approvalSubmit single-line diagram, layout and equipment details for approval where the state requires it.
  2. Build to the approved designInstall with the specified protection, earthing and clearances.
  3. TestInsulation resistance, earth resistance, protection settings and relay tests, recorded on the prescribed formats.
  4. InspectionThe Electrical Inspector inspects the installation and the test records.
  5. Approval to energiseWith approval, the DISCOM completes metering and synchronisation.

Safety on site

  • Permit-to-work and electrical isolation (lock-out, tag-out) before any work on live DC or AC circuits
  • Work-at-height controls on roofs: lifelines, harnesses, edge protection and skylight safety mesh
  • PPE suited to the task: helmets, insulated gloves, safety shoes, eye protection
  • Daily toolbox talks and supervision by trained engineers
  • A safety management system certified to ISO 45001
Earthing and electrical safety works on a solar plant by Arrays Ingenieria
Earthing and electrical safety works on a solar plant: a 25-year plant is only as safe as its earthing and protection.

Need a plant that passes inspection first time? Our veteran-led crews build to the standards and document every test.

Get a free solar quote

Frequently asked questions

Do solar inverters need BIS certification?
Yes. Under the 2025 Quality Control Order, inverters for solar PV applications must carry the BIS Standard Mark. Inverters above 200 kW were given extra time, reportedly to the end of 2026.
Which standards should solar modules meet?
IS 14286 / IEC 61215 for design qualification and IS/IEC 61730 for safety, and ALMM listing where the project falls under the ALMM order.
What is CEIG approval for solar?
Approval by the Electrical Inspector that the installation meets the CEA safety regulations, required before energising plants above the specified voltage or, in many states, above a set capacity.
What tests should be done at commissioning?
Insulation resistance, polarity, string open-circuit voltage and short-circuit current, earth resistance, protection settings and functional checks, documented to IEC 62446-1.

Sources

  1. PIB: MNRE notifies the revised Quality Control Order for solar photovoltaic products
  2. Saur Energy: MNRE extends self-certification for solar inverters above 200 kW
  3. PIB: MNRE amends the ALMM Order 2019 (List-II for solar cells)

This guide explains public policy in plain language for planning purposes. Rules, rates and deadlines change: confirm the current position with the notifying authority, your DISCOM and your tax adviser before you commit. Last checked 11 Oct 2026.

Ingenieria wordmark, Arrays Ingenieria

About the authors. Arrays Ingenieria is an ex-servicemen-led solar EPC and installation & commissioning company working Pan-India, from Assam's tea estates to industrial rooftops. Our story · Our projects

Talk to an engineer

Planning a solar plant? Let's build it together.

CAPEX solar EPC, installation & commissioning and civil works, delivered by an ex-servicemen-led team across India. Tell us about your site and an engineer will get back to you.