DCM Hisar 10 MW ground-mount solar project civil works, Haryana, by Arrays Ingenieria
Case Study · Industrial · Civil Works

DCM Textile, Hisar: Civil Works, Piling and I&C for Solar

Civil works for a 9979 kWp (10 MW) ground-mount solar plant at DCM Textile in Hisar, Haryana.

The Project

About the DCM Hisar, Haryana project

Tata Power issued Arrays Ingenieria the work order on 18 June 2021 for civil works at the 9979 kWp plant. Tata Power has since engaged the company for piling, civil works and installation on projects across India.

DCM has been a repeat site. In 2022 Tata Power Solar engaged Arrays Ingenieria for the installation & commissioning of the 2.1 MW rooftop plant at Hisar, with its CEIG approval, module cleaning system, canopy and conventional earthing.

In 2025-26 the company piled, installed and commissioned a further 500 kWp ground-mount plant at DCM Textile for Tata Power Renewable Energy.

Our scope of work

  • Civil works and pile foundations for the 10 MW ground-mount plant
  • Installation & commissioning of the 2.1 MW rooftop plant
  • Canopy erection and conventional earthing
  • CEIG approval and module cleaning system
  • Piling and I&C of a 500 kWp ground-mount plant (2025-26)

Photos

DCM Hisar 10 MW ground-mount solar project civil works, Haryana, by Arrays Ingenieria
Project Timeline

How the Project Unfolded

The work, stage by stage, as it was ordered and delivered.

  1. 10 MW civil works

    Civil works and pile foundations with pile caps for the 9979 kWp ground-mount plant, and electrical equipment foundations.

  2. 2.1 MW rooftop I&C

    Installation & commissioning of the 2.1 MW rooftop plant, its module cleaning system and CEIG approval.

  3. BOS, canopy and earthing

    Rooftop BOS services, canopy installation and conventional earthing for the 2.1 MWp plant.

  4. Close-out

    Hardware, glands and lugs.

  5. 500 kWp ground-mount

    BOS, installation & commissioning and piling for a further 500.96 kWp ground-mount plant.

On Site

Challenges and How We Handled Them

A repeat site over five years

DCM Textile's Hisar mill brought us back for civil works, a rooftop plant and a ground-mount plant between 2021 and 2025.

Haryana's hard ground

Pile foundations with pile caps were designed for the site's soil and wind loads.

Inspection and safety

CEIG approval and conventional earthing were part of the rooftop scope, so the plant was handed over inspection-ready.

Related

Services Used on This Project

Talk to an engineer

Planning a solar plant? Let's build it together.

CAPEX solar EPC, installation & commissioning and civil works, delivered by an ex-servicemen-led team across India. Tell us about your site and an engineer will get back to you.